520 Update: Evergreen Point Lid Could See Use by Midweek

The State Route 520 Bridge was reopened this morning, after work on the lidded overpasses. The Evergreen Point Road lid could see use by midweek, but won't be complete until December 2013.

State Route 520 reopened this morning after a weekend closure for construction, including work on the new overpass at Evergreen Point Road, which could open to traffic as early as this week, according to the Washington State Department of Transportation (WSDOT).

Construction over the weekend included installation of 40 concrete girders and 300 concrete deck panels on all three lidded overpasses and Bellevue Way.

Crews plan to demolish the exisiting two-lane bridge at Evergreen Point Road and move traffic onto the new 520 lid, which will be completed by December 2013. The demolishing of the existing Evergreen Point Road Bridge is planned for the next weekend closure, which is March 9-12.

Find out what's happening in Kirklandwith free, real-time updates from Patch.

“Putting traffic on the new lid is a big milestone that sets us up to demolish the old, narrow Evergreen Point Road overpass in just two weeks,” said Brian Dobbins, Washington State Department of Transportation SR 520 Eastside construction manager, in a prepared statement.

The weekend's construction included work at all three lidded overpasses and Bellevue Way, according to WSDOT. The state has a Flickr slideshow of the weekend's progress here.

Find out what's happening in Kirklandwith free, real-time updates from Patch.

The lids are part of the state's . Improvements include landscaped lids over portions of 520, a wider roadway, increased carpool lanes, a bicycle and pedestrian lane and environmental upgrades. The construction between Evergreen Point Road to east of 108th Avenue NE in Bellevue will cost $306 million.

The  will incorporate a park and ride, a bus stop, and green space. The other two overpasses are at 84th Avenue Northeast and 92nd Avenue Northeast.

The recently instituted  will pay for some of the construction costs of the highway.

More information

Weekend closure details are available at www.wsdot.wa.gov/Projects/SR520Bridge/WeekendClosures.

More information about the SR 520 Eastside project is online at www.wsdot.wa.gov/Projects/SR520Bridge/MedinaTo202.